The Complete Kitchen Remodel Guide for 2026
Real costs. Real timelines. Real process — based on 50 permitted kitchen projects in Raleigh, NC and over 20 years of renovation experience. No guesswork. No surprises.
2026 Investment Summary
What Does a Kitchen Remodel Cost in Raleigh?
Every kitchen is different — but costs aren’t random. Here’s what Lavish has seen across 50 turn-key, permitted kitchen projects, broken down by category so you can see exactly where your budget goes.
| Category | What it covers | 2026 Range |
|---|---|---|
| Cabinets | Factory finish refacing to fully custom new cabinetry | $15K – $75K |
| Appliances | GE entry-level to Wolf / Sub-Zero professional grade | $15K – $50K |
| Flooring | Patching existing to new hardwoods or tile | $5K – $25K |
| Countertops | Quartz or granite to marble or quartzite | $10K – $25K |
| Plumbing | Replace in place to full relocation and new fixtures | $15K – $30K |
| Lighting | Replace existing to full new layout and fixtures | $15K – $30K |
| HVAC & Mechanical | Floor vents to custom hood ventilation | $5K – $10K |
| Walls, Painting & Structural | Paint refresh to removing or adding walls | $10K – $25K |
| Lavish Design & Implementation | Full design, project management, and coordination | $10K – $20K |
Turn-key average investment range
$100K – $290K
These ranges include everything: design, materials, licensed installers, the permitting process, and project management. When you work with Lavish, there is no separate line item for “general contractor markup” that appears later. What you see above is the complete picture — because we handle it all in-house.
Ranges based on 50 turn-key permitted projects in the Raleigh/Wilmington area. Costs may vary based on scope, structural conditions, and material selections.
The 5-Phase Process
How a Kitchen Remodel Actually Works
Most homeowners are surprised by how much happens before a single wall comes down. Here is how Lavish structures every kitchen remodel — from the first conversation to the final photo shoot.
01
Design & Planning
Everything before construction — land the vision and project plan
Duration
7–13 Weeks
Investment
$15K–$30K
Lavish Hours
30–60 hrs
This is where the real work begins — and where most remodels either succeed or struggle. Before we touch a single wall, our design team works through every detail so that construction is a process of executing a clear plan, not making decisions on the fly. Payment #1 purchases your Lavish design hours to start the process.
02
Invest & Launch
Procure all materials, permits, and set job site expectations
Duration
9–13 Weeks
Investment
$45K–$145K
Lavish Hours
20–30 hrs
This phase is about momentum and preparation. We pull permits (which takes an average of 10–45 days in Wake County), order and schedule delivery of all materials, and establish clear expectations with you about how your home will operate during construction. Payment #2 is tied to the signed construction agreement.
03
Transformation Begins
Demolition, framing, and rough-ins — everything behind the walls
Duration
6–12 Weeks
Investment
$25K–$80K
Lavish Hours
10–20 hrs
Demo day is the milestone clients most look forward to — and the phase that most reveals what’s actually inside the walls. Unforeseen conditions like rot, mold, or out-of-code wiring are addressed here with full transparency. Any additional work is documented and approved before it begins. Payment #3 is due on demo day.
04
Installation
Mid-project inspections passed and all finishes installed
Duration
6–12 Weeks
Investment
$10K–$25K
Lavish Hours
10–20 hrs
This is when your kitchen begins to look like itself. Five inspections must be passed — plumbing, electrical, HVAC, framing, and insulation — before walls close. Then everything you selected in Phase 1 goes in. Payment #4 follows passing those inspections.
05
Last Mile & Extra Mile
Final inspections, adjustments, cleaning, and photo shoot
Duration
4–9 Weeks
Investment
$5K–$10K
Lavish Hours
10–15 hrs
We don’t hand you keys and disappear. This phase is where Lavish earns its name — the final inspections, the punch list, the professional cleaning, the photo shoot, and the leadership sign-off. A 1-year warranty certificate is issued at this phase. Payment #5 follows the final inspection pass.
Timeline Overview
How Long Does a Kitchen Remodel Take?
Total time investment
32 to 59 Weeks
Average full kitchen including design: 7 to 13 months
You may be out of your kitchen for 8 to 16 weeks during active construction
What affects your timeline?
Permit processing (10–45 days in Wake County)
Custom cabinet lead times (8–16 weeks)
Appliance availability and delivery
Unforeseen structural conditions
Countertop template and fabrication (2–3 weeks)
What Homeowners Ask Us Most
Questions Worth Answering Honestly
Why does a kitchen remodel take so long before construction even starts?
What does “$100K to $290K” actually mean — where does that money go?
How long will we be without a working kitchen?
What is a permitted kitchen remodel and why does it matter?
What happens if something unexpected is found behind the walls?